Start to Finish

Our Kitchen Remodel Process in Portland, OR

Seven steps, no guesswork. Here’s exactly what happens between your first call and the final walkthrough — including the parts most contractors don’t explain up front.

Get a Free Quote
How It Works

The Seven Steps, In Order

Every kitchen remodeling Portland project we take on follows this same sequence, whether it’s a refresh or a full renovation.

  1. Week 1

    Initial Consultation & Walkthrough

    We walk the space with you, talk through what’s working and what isn’t, and take rough measurements. This is also when we flag anything visible that could affect scope — an old panel, visible water staining, a layout constraint. No cost yet, just an honest first look.

  2. Weeks 2–4

    Design & Material Selection

    Layout, cabinet style, countertop material, and finishes get decided here. We provide a detailed, line-itemized quote based on your actual selections — not a rough estimate you’ll renegotiate later. See our full pricing guide for what drives cost at this stage.

  3. Weeks 4–14 (runs in parallel)

    Permitting

    We submit and manage the permit application with the City of Portland’s Bureau of Development Services ourselves — you’re not the one on hold with the city. Review time averages around 70 days for anything touching structural, electrical, or plumbing work. Cosmetic-only projects usually skip this step.

  4. Overlaps with permitting

    Material Ordering

    Cabinets, countertops, and appliances get ordered once selections are finalized, since custom and semi-custom cabinetry often has its own lead time separate from the permit timeline. Ordering early keeps this from becoming the bottleneck later.

  5. 1–3 days

    Demolition

    Old cabinets, countertops, and flooring come out. This is also when anything hidden behind the walls — old wiring, corroded plumbing, water damage — actually becomes visible. If we find something, we tell you before continuing, not after.

  6. 2–5 weeks, scope-dependent

    Construction

    Rough-in electrical and plumbing happens first, followed by drywall, flooring, cabinet installation, countertops, and finish work in that order. Larger structural changes extend this phase; a cosmetic refresh moves through it much faster.

  7. Final day

    Final Walkthrough

    We walk the finished kitchen with you, work through a punch list of any small fixes, and don’t consider the project done until that list is clear. For what daily life looks like during these phases, see our guide to living through a remodel.

Timeline Summary

How Long Does Each Phase Actually Take?

PhaseTypical DurationNotes
Consultation & design2–4 weeksFaster if you already know your material choices
Permitting~70 days averageSkipped entirely for cosmetic-only work
Material lead time3–8 weeksRuns alongside permitting, not after it
Demolition1–3 daysLonger for full-kitchen structural demo
Construction2–5 weeksCosmetic refresh is fastest; structural work is slowest
Total, start to finish4–6 monthsDesign-to-completion, most projects
Can the permitting and construction phases overlap? No — permitted work can’t legally start until the permit is issued. Design, material selection, and ordering can all happen while permitting is in progress, which is how we keep the overall timeline as short as it can reasonably be.
Questions

Frequently Asked Questions

Do I need to be home during construction?

Not for most of it. We’ll coordinate access in advance, and you don’t need to be present for routine work — just reachable if a decision comes up.

What happens if you find something unexpected once demo starts?

We stop, show you what we found, and explain the cost and timeline impact before doing anything further. Nothing gets added to the project without your approval first.

Can I make changes once construction has started?

Sometimes, but it depends on the phase. Changes before rough-in is complete are usually straightforward; changes after cabinets or countertops are ordered can affect both cost and timeline.

Who handles the permit paperwork?

We do, start to finish — submission, responding to any city review comments, and scheduling inspections. It’s part of the process, not an extra step you manage yourself.

What the Process Was Actually Like

Real Clients on Working Through Our Process

Not just the finished kitchen — what it was like to get there.

“We knew going in that permitting would take a while, because they told us upfront instead of promising a faster timeline just to win the job. When it took about as long as they said, there were no surprises.”

Sarah & Mark
Sellwood-Moreland

“My kitchen is small, so I was worried the design phase would drag on. It didn’t — we landed on a layout in a couple of meetings, and once materials were ordered, construction moved fast.”

James Wilson
Alberta Arts District

“When they opened a wall and found something unexpected, they stopped and called us before doing anything else. That’s the part of the process I’d tell other homeowners to ask about before hiring anyone.”